Update - 4th September:
Neither closures have approval from the Highland Council yet - comments/concerns on the proposed closure should be emailed Highland Council's Road Operations Team here.
(Note: For information on the TTRO procedure go to the Highland Council Website and also an interactive map of approved TTRO works can be found at Roadworks Scotland).
SSEN's latest information:
Closure of A831 (Beauly - Cannich) road section at Balblair Substation -
The proposed temporary road closures are as follows:
Closure 1
• Friday 18 September, 1:30pm to Monday 21 September, 10:30pm
Closure 2
• Friday 02 October, 1:30pm to Monday 05 October, 10:30pm
The road will reopen between these closures to allow normal traffic movements to resume.
Detailed information can be found on the SSEN "Beauly 132kv Reenforcement Project" webpage in the "Project Updates" tab including proposed road diversion map.
Closure of the C1106 over Black Bridge for inspection works:
The extensive closures planned by SSEN for September and October were withdrawn (for now) via email to the "Fanellan Engagement" list on 2nd September - we await further updates.
SSEN Survey archeology survey works at Butlers Field:
SSEN Survey works Black Bridge & Fanellan Road:
SSEN compound changes before and after Christmas:
A Scottish Water notification but will affect the area
Received by email on 14th October - Beaufort route survey:
Received by email on 14th October - other movements and survey work:
Various traffic movements from end of August to the end of 2025 for archaeological pits on the site PLUS UPDATED INFO RECEIVED 2nd September:
Received by email on 14th October - Excavation work and trial blasting:
Received by email on 8th September:
From 10 pm on Tuesday 19th August to 6am on Wednesday 20th August - overnight closure of Black Bridge for survey work - see below.
Tuesday 1st and Thursday 3rd July Abnormal Loads from Invergordon to Balblair Substation via Beauly
Plant movement and works in Butlers Field (Fanellan Road junction near Black Bridge)
Bridge Inspection works in May 2025 on the way out of Kiltarlity towards Fanellan
Underground Cable Inspection Works for 18wks - notice received in the post from SSEN